Schedule & Calendar

  • January 2017 to May 2017: Telecommunications and electrical companies relocated utilities.
  • Spring through Fall 2017: Contract awarded to CCS Constructors, Inc. Majority of US 2 is reconstructed (underlying concrete slab removed, and a base paving layer and new sidewalk installed); temporary bridge installed.
  • 2018: New bridge will be constructed and drainage northeast of VT14 bridge will be installed. Temporary bridge will be removed in December 2018/January 2019.
  • 2019: Site disrupted by project will be restored, with new landscaping installed. US 2 will receive its final layer of paving.